2008 Startup Schedule
(Revision 3)


Pick from calendar
 
Task
Start
Stop
H+
H+ ion sources ready for interlock checks
2-May
H+ 01BL01 Mode ERCs due
2-May
Perform H+ 01BL mode interlock checks 3-May 6-May
H+ 211 Mode ERCs due
5-May
Perform H+ 211 mode interlock checks 6-May 10-May
Tune LEBT (TA) to 01BL Mode 6-May 8-May
Tune H+ low peak to 211 mode 10-May 12-May
IPF ERCs due
14-May
Perform IPF interlock checks 15-May 19-May
Tune to IPF 19-May 20-May
H-
H- ion source ready for interlock checks
2-May
H- 01BL01 Mode ERCs due
2-May
Perform H- 01BL mode interlock checks 3-May 6-May
H- 211 Mode ERCs due
5-May
Tune LEBT (TB) to 01BL Mode 6-May 8-May
Perform H- 211 mode interlock checks 6-May 10-May
800 Mode ERCs due
7-May
Perform 800 mode interlock checks 8-May 12-May
211 mode RF systems turned over to OPS
8-May
LDN-RIKI/RIBS/TUBS ERCs due
9-May
800 mode RF systems turned over to OPS
9-May
Perform TUBS mode interlock checks 10-May 15-May
Tune H- low peak to 211 mode 10-May 12-May
Tune H- low peak to 800 mode 12-May 14-May
211 and 800 mode high peak tune 14-May 15-May
Line X/B/C ERCs due
13-May
Perform Line X/B/C mode interlock checks 14-May 19-May
Tune to RIBS/TUBS mode 15-May 19-May
Target 1 ERCs due
15-May
Perform Target 1 interlock checks 16-May 21-May
Tune to Line B/C 19-May 20-May
Target 2/4 ERCs due
19-May
Perform Target 2/4 interlock checks 20-May 24-May
Tune low current to 1L 21-May 22-May
Tune for Production to 1L 22-May 25-May
Tune to Target 2/4 24-May 25-May
Tuning contingency 25-May 27-May
Instrument checkout and radiation surveys 27-May 29-May
Source recycle 29-May 1-Jun
Tune recovery to all areas 1-Jun 2-Jun
Production beam to all areas
2-Jun

Updated: 04-16-2008