Task
|
Start
|
Stop
|
H+
|
|
H+ ion sources ready for interlock checks
|
|
2-May
|
|
H+ 01BL01 Mode ERCs due
|
|
2-May
|
|
Perform H+ 01BL mode interlock checks
|
3-May
|
6-May
|
|
H+ 211 Mode ERCs due
|
|
5-May
|
|
Perform H+ 211 mode interlock checks
|
6-May
|
10-May
|
|
Tune LEBT (TA) to 01BL Mode
|
6-May
|
8-May
|
|
Tune H+ low peak to 211 mode
|
10-May
|
12-May
|
|
IPF ERCs due
|
|
14-May
|
|
Perform IPF interlock checks
|
15-May
|
19-May
|
|
Tune to IPF
|
19-May
|
20-May
|
H-
|
|
H- ion source ready for interlock checks
|
|
2-May
|
|
H- 01BL01 Mode ERCs due
|
|
2-May
|
|
Perform H- 01BL mode interlock checks
|
3-May
|
6-May
|
|
H- 211 Mode ERCs due
|
|
5-May
|
|
Tune LEBT (TB) to 01BL Mode
|
6-May
|
8-May
|
|
Perform H- 211 mode interlock checks
|
6-May
|
10-May
|
|
800 Mode ERCs due
|
|
7-May
|
|
Perform 800 mode interlock checks
|
8-May
|
12-May
|
|
211 mode RF systems turned over to OPS
|
|
8-May
|
|
LDN-RIKI/RIBS/TUBS ERCs due
|
|
9-May
|
|
800 mode RF systems turned over to OPS
|
|
9-May
|
|
Perform TUBS mode interlock checks
|
10-May
|
15-May
|
|
Tune H- low peak to 211 mode
|
10-May
|
12-May
|
|
Tune H- low peak to 800 mode
|
12-May
|
14-May
|
|
211 and 800 mode high peak tune
|
14-May
|
15-May
|
|
Line X/B/C ERCs due
|
|
13-May
|
|
Perform Line X/B/C mode interlock checks
|
14-May
|
19-May
|
|
Tune to RIBS/TUBS mode
|
15-May
|
19-May
|
|
Target 1 ERCs due
|
|
15-May
|
|
Perform Target 1 interlock checks
|
16-May
|
21-May
|
|
Tune to Line B/C
|
19-May
|
20-May
|
|
Target 2/4 ERCs due
|
|
19-May
|
|
Perform Target 2/4 interlock checks
|
20-May
|
24-May
|
|
Tune low current to 1L
|
21-May
|
22-May
|
|
Tune for Production to 1L
|
22-May
|
25-May
|
|
Tune to Target 2/4
|
24-May
|
25-May
|
|
Tuning contingency
|
25-May
|
27-May
|
|
Instrument checkout and radiation surveys
|
27-May
|
29-May
|
|
Source recycle
|
29-May
|
1-Jun
|
|
Tune recovery to all areas
|
1-Jun
|
2-Jun
|
|
Production beam to all areas
|
|
2-Jun
|